Case File 26-0685
View full legal title
Discussion and action on a Resolution that the City Council hereby accepts the State Infrastructure Bank loan agreement in its substantially final form in order to secure receipt of funds in the amount of Six Million Dollars ($6,000,000.00), to be fully repaid over no more than twenty five (25) years, for SIB loan number S2026-001-05 Traffic Management Center Upgrades Phase 2-5, to finance the City’s local match and actual cost of construction of the Project, that the City Council hereby authorizes the City Manager to execute the State Infrastructure Bank loan agreement, together with all required documentation, to effectuate the City’s intent to borrow such funds, and that the City Council further authorizes the City Manager to take or perform any actions required for implementation of this Resolution to receive funding from the State Infrastructure Bank and authorizes the City Manager, or designee, to effectuate any budget transfers and execute any contracts and/or related documents necessary to ensure that the funds are properly expended. [POSTPONED FROM 06-09-2026]
Get notified on new hearings, votes, or status changes for this matter.
Actions
Showing all 5 actions. Filter by: , , , , .
Submit ratepayer terms before Northeast El Paso data center deal closes
Context: Council directed the City Manager and City Attorney on 2026-06-23 (8-0) to negotiate the CBA with a draft due back within 45 days, putting the deadline around 2026-08-07.
Recommended: File formal comments with the City Attorney's office now, while the Community Benefits Agreement for Meta's Northeast El Paso data center is still being drafted — once Council votes to adopt the final terms covering water/electric infrastructure and ratepayer protection, they're locked in with no further public input step.
Bid on Railroad Drive and Sun Valley Street infrastructure work
Context: Council approved three SIB loans totaling $10.55 million on 2026-06-23 for these specific projects after a six-week postponement from 2026-06-09.
Recommended: Contact the city's capital projects office now that funding is confirmed — the $10.55 million in State Infrastructure Bank loans approved 8-0 on June 23 covers Railroad Drive, Sun Valley Street, and the Traffic Management Center, projects that had been stalled since being postponed from the June 9 meeting.
Request draft terms for Northeast El Paso data center deal
Context: The 2026-06-23 8-0 vote set a 45-day deadline for the CBA draft with negotiation authority held entirely by the City Manager and City Attorney.
Recommended: File a records request for the draft Community Benefits Agreement terms sheet now — the directive names water/electric infrastructure, ratepayer protection, and workforce development as covered topics but the minutes show no public review step before the draft comes back to Council.
Target City Manager during Northeast El Paso data center talks
Context: The 2026-06-23 directive assigns CBA negotiation authority specifically to the City Manager and City Attorney with a 45-day deadline (~2026-08-07), not to Council as a body.
Recommended: Reach the City Manager and City Attorney directly over the next two weeks — they hold sole authority to negotiate the Meta data center Community Benefits Agreement terms before it returns to Council for a final vote, a narrower channel than lobbying Council after the draft is set.
Watch for construction on Railroad Drive and Sun Valley Street
Context: The three SIB-funded street and traffic projects postponed from the June 9 meeting were approved 8-0 on 2026-06-23.
Recommended: Expect road work notices on these two streets soon — the city just cleared $10.55 million in financing after a six-week delay, so construction that had been on hold since June 9 can now proceed.
Key Entities
View relationship map
Loading relationship map…
Timeline
Discussion and action on a Resolution that the City Council hereby accepts the State Infrastructure Bank loan agreement in its substantially final form in order to secure receipt of funds in the amount of Six Million Dollars ($6,000,000.00), to be fully repaid over no more than twenty five (25) years, for SIB loan number S2026-001-05 Traffic Management Center Upgrades Phase 2-5, to finance the City’s local match and actual cost of construction of the Project, that the City Council hereby authorizes the City Manager to execute the State Infrastructure Bank loan agreement, together with all required documentation, to effectuate the City’s intent to borrow such funds, and that the City Council further authorizes the City Manager to take or perform any actions required for implementation of this Resolution to receive funding from the State Infrastructure Bank and authorizes the City Manager, or designee, to effectuate any budget transfers and execute any contracts and/or related documents necessary to ensure that the funds are properly expended. [POSTPONED FROM 06-09-2026]
Vote: 8 for, 0 against
approve the Resolution accepting State Infrastructure Bank loan
Discussion and action on a Resolution that the City Council hereby accepts the State Infrastructure Bank loan agreement in its substantially final form in order to secure receipt of funds in the amount of Six Million Dollars ($6,000,000.00), to be fully repaid over no more than twenty five (25) years, for SIB loan number S2026-001-05 Traffic Management Center Upgrades Phase 2-5, to finance the City’s local match and actual cost of construction of the Project, that the City Council hereby authorizes the City Manager to execute the State Infrastructure Bank loan agreement, together with all required documentation, to effectuate the City’s intent to borrow such funds, and that the City Council further authorizes the City Manager to take or perform any actions required for implementation of this Resolution to receive funding from the State Infrastructure Bank and authorizes the City Manager, or designee, to effectuate any budget transfers and execute any contracts and/or related documents necessary to ensure that the funds are properly expended. [POSTPONED FROM 06-09-2026]
Vote: 7 for, 0 against, 1 absent
postpone two weeks discussion on accepting SIB loan S2026-001-05 for $6,000,000 for Traffic Management Center Upgrades Phase 2-5
*Consent-style motion, maker and seconder not named in minutes