Case File 26-0687
View full legal title
Discussion and action on the results of Round 10 of the Hotel Occupancy Tax Audit. [POSTPONED FROM 06-09-2026]
Get notified on new hearings, votes, or status changes for this matter.
Actions
Showing all 4 actions. Filter by: , , , .
Review Draft Meta Data Center Agreement in Northeast El Paso
Context: The 8-0 vote (Limón/Fierro) set a 45-day negotiation deadline (~Aug. 7, 2026) without specifying enforcement terms in the public record.
Recommended: Council's June 23 order directs the City Manager and City Attorney to negotiate a Community Benefits Agreement with Meta for the Northeast El Paso data center, covering water/electric infrastructure and ratepayer protection, but the order lists only topics, not enforceable terms. Request the draft as soon as it returns — due within 45 days, around August 7, 2026 — and check whether ratepayer protection and workforce commitments are binding obligations or just aspirational language before it comes back for a Council vote.
Question Undefined Terms in Northeast El Paso Data Center Deal
Context: The June 23 order sets a 45-day CBA draft deadline but the public record has no specific negotiating terms or benchmarks attached.
Recommended: Council approved 8-0 a directive naming broad CBA topics — water/electric infrastructure, ratepayer protection, workforce development — with Meta, but the record contains no dollar figures, enforcement mechanism, or scheduled public hearing before the 45-day deadline (~Aug. 7). File a request now for the negotiation parameters staff are working from, since residents currently have no way to see what 'ratepayer protection' will actually mean in practice.
Lobby City Manager on Northeast El Paso Data Center Deal
Context: The June 23 8-0 order delegates term-setting to staff with a 45-day return deadline, ahead of any scheduled public hearing on the agreement's contents.
Recommended: Council routed CBA negotiation with Meta directly to the City Manager and City Attorney rather than a committee or public hearing, with a draft due back in 45 days (~Aug. 7). Workforce-development and ratepayer-advocacy groups should engage the City Manager's office now, because once the draft returns, Council's role is likely a single up-or-down vote rather than renegotiation.
Track Who Pays for Northeast El Paso Data Center Utilities
Context: Council's June 23 order names ratepayer protection as a required CBA component but leaves the funding mechanism undefined, with a draft due in 45 days.
Recommended: The Community Benefits Agreement being negotiated with Meta is supposed to include 'ratepayer protection,' which decides whether you or Meta covers the cost of the water and electric infrastructure the data center needs. Watch for the draft agreement due back within 45 days (around August 7, 2026) to see whether that protection is a real guarantee or just a stated goal.
Key Entities
Timeline
Discussion and action on the results of Round 10 of the Hotel Occupancy Tax Audit. [POSTPONED FROM 06-09-2026]
Vote: 8 for, 0 against
accept the Round 10 Hotel Occupancy Tax Audit results
Discussion and action on the results of Round 10 of the Hotel Occupancy Tax Audit. [POSTPONED FROM 06-09-2026]
Vote: 7 for, 0 against, 1 absent
postpone two weeks discussion on Round 10 of Hotel Occupancy Tax Audit
*Consent-style motion, maker and seconder not named in minutes