Marina Capital Improvement Projects Updates (26-1178)
View full legal title
Capital Improvement Projects Updates
Get notified on new hearings, votes, or status changes for this matter.
Actions
Showing all 2 actions. Filter by: , .
Verify marina boater facility schedule slip and demolition timeline
Why now: At the 2026-09-14 meeting Mr. Atwood said the Coopers boater's facility is about 2 weeks behind but will make April 2027, while asbestos removal was only scheduled for late September before demolition of the haul out facility could begin, and the project was described as taking 18 months to 2 years.
What to do: Ask marina staff for the contractor's current schedule and the asbestos abatement contract, and reconcile them against what was reported publicly. The record gives an April 2027 completion date alongside an 18-month-to-2-year project timeline, and both cannot easily be true.
Act before: After the requested records are produced
Check marina construction effects on haul out access
Applies if: You use the marina's haul out services or the L-head area
Why now: The 2026-09-14 update states the haul out facility was emptied before Labor Day, its contents sit in two 40' connex boxes on the L-head, and demolition follows asbestos removal scheduled for the end of September.
What to do: If you keep a boat at the marina, ask staff where haul out services are now handled and when the L-head storage ends. The haul out facility was emptied before Labor Day and its contents are in two 40' shipping containers on the L-head.
Act before: After the next material record update
Timeline
Capital Improvement Projects Updates
Vote: 0 for, 0 against
staff update on capital improvement projects; discussion only, no action