Municue

2026 Asphalt Resurfacing Contract 3

project
1 mention across 1 event
1 eventLast active Tracked since

Key facts

Latest action

· City Council Meeting

2026 Asphalt Resurfacing Contract 3 - Change Order 1

Result: Approved.

Topics

transportation (1)
contract (1)

Roles

mentioned (1)
View network map

Loading network map…

Activity Timeline

August 2026

Award Of Contract - Consent Items

Authorizes Change Order No. 1 of $677,183.40 and 60 additional calendar days to the construction contract with Peachtree Construction, Ltd. for the 2026 Asphalt Resurfacing Contract 3 project, revising the contract to $3,675,727.90 to allow full-depth rehabilitation on Acapulco Road and additional concrete repairs.

2026 Asphalt Resurfacing Contract 3 - Change Order 1