Big Fossil Creek Collector Parallel, Phase IV A Project

project
1 mention across 1 event
1 eventLast active Tracked since $789K city spending

Topic Distribution

Topics

utilities (1)
contract (1)
development (1)
budget (1)

Roles

mentioned (1)

Activity Timeline

March 2026

Award Of Contract Consent

Authorizes a $788,973 construction contract with R & D Burns Brothers for the Big Fossil Creek Collector Parallel, Phase IV A Project, and adopts appropriation ordinances for the Water Department's FY2026–2030 CIP contribution.

(CD 11) Authorize Execution of a Contract with R & D Burns Brothers, Inc. in the Amount of $788,973.00, for Big Fossil Creek Collector Parallel, Phase IV A Project, Adopt Appropriation Ordinances to E

$789K