Fort Worth Central City Part 14 - Channel Segment C, Sanitary Sewer Relocation
project
1 mention across 1 event
1 eventLast active Tracked since $3.5M city spending
Topic Distribution
Topics
utilities (1)
contract (1)
development (1)
budget (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
March 2026
Award Of Contract Consent
Authorizes Change Order No. 2 adding $3,526,707.28 to an existing contract with S.J. Louis Construction of Texas, Ltd. for sanitary sewer relocation work on the Fort Worth Central City Part 14 - Channel Segment C project, while also adopting a resolution for future debt reimbursement and an appropriation ordinance for Water's capital improvement program contribution.
…3,526,707.28 to a Contract with S.J. Louis Construction of Texas, Ltd., for the Fort Worth Central City Part 14 - Channel Segment C, Sanitary Sewer Relocation, Adopt a Resolution Expressing Official Intent to Reimburse Expenditures with P…
$3.5M