Municue

Hampshire Boulevard Water and Sanitary Sewer Replacements Project

project
1 mention across 1 event
1 eventLast active Tracked since

Topic Distribution

Topics

utilities (1)
contract (1)
budget (1)

Roles

mentioned (1)

Activity Timeline

September 2026

General - Consent Items

Council authorizes Amendment No. 2 to the Neel-Schaffer engineering agreement for the Hampshire Boulevard water main and sanitary sewer replacement, raising the contract to $809,516, and appropriates $77,892 from Water & Sewer PayGo funds.

…haffer, Inc. for the Cast Iron Water Main and Sanitary Sewer Replacement in the Hampshire Boulevard Water and Sanitary Sewer Replacements Project for a Revised Amount of $809,516.00, and Adopt Appropriation Ordinance to Effec…