October 2026
Award Of Contract - Consent Items
Authorizes Amendment No. 2 to Freese and Nichols' engineering agreement for design of the Lebow Channel Flood Mitigation project, raising the contract to $9,625,059, with an appropriation ordinance and CIP amendment funded by shifting money from the Large Flood Mitigation programmable project.
Freese and Nichols, Inc. Engineering Agreement Amendment No. 2 for Lebow Channel Flood Mitigation
$9.6M