2 mentions across 2 events
2 eventsLast active Tracked since $978K city spending

Mention Frequency

Topic Distribution

Topics

utilities (2)
budget (2)
contract (1)

Roles

mentioned (2)

Activity Timeline

March 2026

Award Of Contract Consent

Appropriation of $700,000 to cover increased project costs for the M-199 C-R Sanitary Sewer Parallel Interceptor Project as part of the City's FY2026-2030 Capital Improvement Program.

(CD 7) Adopt Appropriation Ordinance in the Amount of $700,000.00 for Increased Project Costs for the M-199 C-R Sanitary Sewer Parallel Interceptor Project to Effect a Portion of Water’s Contribution

$700K

January 2026

Award Of Contract Consent

Authorizes Amendment No. 3 to an engineering agreement with Kimley-Horn and Associates, Inc., adding $278,400 for water and sanitary sewer replacement work on the Marine Creek Sanitary Sewer Parallel Interceptor Project. Also adopts an appropriation ordinance to fund this amendment as part of the FY2026-2030 Capital Improvement Program.

…th Kimley-Horn and Associates, Inc. for Water and Sanitary Sewer Replacement on Marine Creek Sanitary Sewer Parallel Interceptor Project and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution t…

$278K