Risk Insurance Claim Residual
project
1 mention across 1 event
1 eventLast active Tracked since $5.2M city spending
Topic Distribution
Topics
utilities (1)
public safety (1)
budget (1)
Roles
mentioned (1)
Related Entities
View network map
Loading network map…
Activity Timeline
October 2026
General - Consent Items
Closes out the 2021 Winter Storm Uri insurance claim by transferring $5,160,496.96 in insurance proceeds to the Water and Sewer Fund to reimburse repair costs and $156,854.87 in remaining proceeds to the Risk Financing Fund.
…in the amount of $156,854.87 from the General Capital Projects Fund within the Risk Insurance Claim Residual project (City Project No. 103590) to the Risk Financing Fund to complete the cl…
$5.2M