June 2026
The city authorizes acquisition of permanent water easements (1.2696 acres) and temporary construction easements (0.8162 acres) from Paslay Ventures, Inc. at three properties on East Rendon Crowley Road in Burleson for the Southside II Water Main Alignment City Transmission Main Project, at a total cost of $244,262.
…sing Costs in an Amount Up to $2,500.00 for a Total Cost of $244,262.00 for the Southside II Water Main Alignment City Transmission Main Project
March 2026
Authorizes Amendment No. 1 adding $635,393.00 to an engineering agreement with Kimley-Horn and Associates for design of the Southside II Water Main Alignment Study Project, bringing the revised total to $2,983,794.00.
(CD 6 and CD 8) Authorize Execution of Amendment No. 1 in the Amount of $635,393.00 to an Engineering Agreement with Kimley-Horn and Associates, Inc. for Design of the Southside II Water Main Alignmen