Activity Timeline

April 2026

Eminent Domain

Approves eminent domain proceedings to acquire a permanent electric easement for the CKT961 Induction Reduction Project, mitigating induced voltage on the CapMetro Red Rail Line.

…trum Drive, Austin, Texas 78717. The general route of the project begins at the Jollyville Substation and runs parallel to the CapMetro Red Line, crossing over Ranch Road 620 North…

$61K
Eminent Domain

Authorizes eminent domain proceedings to acquire a permanent electric transmission and distribution easement for the CKT961 Induction Reduction Project. The easement will mitigate induced voltage from Austin Energy Circuit 961 near the CapMetro Red Rail Line.

…uilding 3, Austin, Texas, 78717. The general route of the project begins at the Jollyville Substation and runs parallel to the CapMetro Red Line, crossing over Ranch Road 620 North…

$126K
Eminent Domain

Authorizes eminent domain proceedings to acquire a permanent electric transmission and distribution easement for the CKT961 Induction Reduction Project. The easement will mitigate induced voltage from Austin Energy Circuit 961 near the CapMetro Red Rail Line.

…uilding 2, Austin, Texas, 78717. The general route of the project begins at the Jollyville Substation and runs parallel to the CapMetro Red Line, crossing over Ranch Road 620 North…

$106K

February 2026

Eminent Domain

Authorizes eminent domain proceedings to acquire a permanent access easement for the CKT961 Induction Reduction Project, which will mitigate induced voltage from an Austin Energy transmission line on the Cap Metro Red Rail Line. The acquisition concerns property owned by TREA SH Ranch, LLC and is currently appraised at $119,432.

…armer Lane, Austin, Texas 78717. The general route of the project begins at the Jollyville Substation and runs along the Cap Metro Red Rail Line, ending at the Ashton Woods Substati…

$119K