Austin Convention Center
Key facts
- Latest action
· City Council
Amount: $2.3M
- Money
$5.0M in total financial activity across agenda items that mention this organization.
Largest single item: $2.7M on (Authorize a construction-services contract for the Second Street Garage Exterior Improvements Project. RS Ellis d/b/a Southwest Corporation would receive up to $2,973,318, including contingency…)
- Cases
- Palmer Events Center Garage Structural Repairs Contract (26-2478) — active, last event
- Second Street Garage Exterior Improvements Contract (26-1229) — inactive, last event
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
Connected Matters
Legislative threads where Austin Convention Center is mentioned
Palmer Events Center Garage Structural Repairs Contract (26-2478)
Second Street Garage Exterior Improvements Contract (26-1229)
View network map
Loading network map…
Activity Timeline
September 2026
Ratifies a construction contract with Jay-Reese Contractors, Inc. for the Palmer Events Center Garage Structural Repairs Project, not to exceed $2,265,105.
…xceed $2,265,105. Funding: $2,265,105 is available in the Capital Budget of the Austin Convention Center. FSDCentralProcurementRCAs@austintexas.gov
March 2026
Authorize a construction-services contract for the Second Street Garage Exterior Improvements Project. RS Ellis d/b/a Southwest Corporation would receive up to $2,973,318, including contingency, funded through the Austin Convention Center capital budget.
…xceed $2,973,318. Funding: $2,973,318 is available in the Capital Budget of the Austin Convention Center and is not associated with or funded by the Convention Center Expansion Project…