Amount: $344.0M
- Money
$362.0M in total financial activity across agenda items that mention this project.
Largest single item: $344.0M on (Amendment to the construction contract with Sundt/Archer Western for the Airport Expansion and Development Program Utility Infrastructure Campus Wide Project, increasing it by $224,000,000 to a…)
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
View network map
Loading network map…
Activity Timeline
October 2026
Amendment to the construction contract with Sundt/Archer Western for the Airport Expansion and Development Program Utility Infrastructure Campus Wide Project, increasing it by $224,000,000 to a revised total of $344,000,000.
Authorize an amendment to the construction contract for the Airport Expansion and Development Program Utility Infrastructure Campus Wide Project for Austin Aviation with Sundt/Archer Western, to incre
January 2026
Authorizes an $18 million amendment with HDR Engineering, Inc. for utility infrastructure work under Austin Aviation's Airport Expansion and Development Program, raising the contract ceiling to $28 million.
Authorize an amendment to the contract for the Airport Expansion and Development Program Utility Infrastructure Campus Wide Project for Austin Aviation with HDR Engineering, Inc., to increase the amou