Key facts

Money

$5.1M in total financial activity across agenda items that mention this project.

Largest single item: $5.1M on (Authorizes construction services for the Oltorf at Travis Heights Pressure Zone Conversion Project, including contingency funding, for Austin Water.)

Topic Distribution

Topics

utilities (1)
development (1)
budget (1)
contract (1)

Roles

mentioned (1)
View network map

Loading network map…

Activity Timeline

May 2026

Consent

Authorizes construction services for the Oltorf at Travis Heights Pressure Zone Conversion Project, including contingency funding, for Austin Water.

Authorize a contract for construction services for the Oltorf at Travis Heights Pressure Zone Conversion Project for Austin Water with Facilities Rehabilitation, Inc., in the amount of $5,073,625, plu