Upper Harris Branch Interceptor Project
Key facts
- Latest action
· City Council
Amount: $980K
- Money
$980K in total financial activity across agenda items that mention this project.
Largest single item: $980K on (Authorize a $979,529 amendment to Doucet & Associates, Inc.'s engineering-services contract for Austin Water's Upper Harris Branch Interceptor Project, increasing the contract ceiling to $4,044,907…)
Topic Distribution
Topics
Roles
View network map
Loading network map…
Activity Timeline
March 2026
Authorize a $979,529 amendment to Doucet & Associates, Inc.'s engineering-services contract for Austin Water's Upper Harris Branch Interceptor Project, increasing the contract ceiling to $4,044,907. The amendment is funded through Austin Water's Capital Budget.
Authorize an amendment to the contract for engineering services for the Upper Harris Branch Interceptor Project for Austin Water with Doucet & Associates, Inc., in the amount of $979,529, for a revise