Brown Road Water Treatment Plant
Key facts
- Latest action
· City Council
Amount: $13.5M
- Money
$13.5M in total financial activity across agenda items that mention this location.
Largest single item: $13.5M on (Council is asked to award a CMAR Guaranteed Maximum Price No. 7 contract to Garney Companies for procuring and installing one mile of 36-inch waterline for the Central Mesa Reuse Pipeline and East…)
Topic Distribution
Topics
Roles
Related Entities
View network map
Loading network map…
Activity Timeline
July 2026
Council is asked to award a CMAR Guaranteed Maximum Price No. 7 contract to Garney Companies for procuring and installing one mile of 36-inch waterline for the Central Mesa Reuse Pipeline and East Mesa Interconnect Pipeline projects, plus a change order allowance. The pipeline provides interconnected capacity during Brown Road Water Treatment Plant outages, Colorado River reductions, or CAP Canal dry ups.
…ne will allow for critical interconnected capacity during either outages at the Brown Road Water Treatment Plant, during reductions of Colorado River Water, or CAP Canal system dry ups.