1 mention across 1 event
1 eventLast active Tracked since $13.5M city spending

Key facts

Topic Distribution

Topics

utilities (1)
development (1)
contract (1)

Roles

mentioned (1)
View network map

Loading network map…

Activity Timeline

July 2026

Contract

Council is asked to award a CMAR Guaranteed Maximum Price No. 7 contract to Garney Companies for procuring and installing one mile of 36-inch waterline for the Central Mesa Reuse Pipeline and East Mesa Interconnect Pipeline projects, plus a change order allowance. The pipeline provides interconnected capacity during Brown Road Water Treatment Plant outages, Colorado River reductions, or CAP Canal dry ups.

Central Mesa Reuse Pipeline Project and East Mesa Interconnect Pipeline Project, Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 7 of 7. (Districts 1 and 2) GMP No. 7 includes

$13.5M