Bachman Dam and Spillway Improvement Project
Also known as: Bachman Lake Dam and Spillway Rehabilitation Project
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
View network map
Loading network map…
Activity Timeline
May 2026
Authorizes a $809,519.08 increase to the construction services contract with Rebcon, LLC for additional work on the Bachman Dam and Spillway Improvement Project, bringing the total contract to $45,006,075.80, split between the Water Capital Improvement F Fund and the Water Construction Fund.
Authorize an increase in the construction services contract with Rebcon, LLC for additional work associated with the Bachman Dam and Spillway Improvement Project - Not to exceed $809,519.08, from $44,
Authorizes a $809,519.08 increase in the construction services contract with Rebcon, LLC for additional work on the Bachman Dam and Spillway Improvement Project, raising the contract ceiling from $44,196,556.72 to $45,006,075.80, financed through the Water Capital Improvement F Fund and Water Construction Fund.
Authorize an increase in the construction services contract with Rebcon, LLC for additional work associated with the Bachman Dam and Spillway Improvement Project - Not to exceed $809,519.08, from $44,
October 2025
Authorizes a ~$1M increase to the construction services contract with Rebcon LLC for additional work on the Bachman Dam and Spillway Improvement Project, raising the total contract to $44,196,556.72.
Authorize an increase in the construction services contract with Rebcon LLC for additional work associated with the Bachman Dam and Spillway Improvement Project - Not to exceed $1,017,556.72, from $43
Authorization to increase the construction services contract with Rebcon LLC by $1,017,556.72 for additional work on the Bachman Dam and Spillway Improvement Project, raising the total from $43,179,000.00 to $44,196,556.72, funded by the Water Construction Fund.
Dallas Water Utilities: Authorize an increase in the construction services contract with Rebcon LLC for additional work associated with the Bachman Dam and Spillway Improvement Project not to exceed $