· City Council
Result: Approved · Amount: $3.3M
- Money
$6.6M in total financial activity across agenda items that mention this project.
Largest single item: $3.3M on (Authorizes a ~$3.3M increase to the construction services contract with Ragle, Inc. for additional work on the Cadiz Street and Riverfront Boulevard Bridge Improvements, raising the total contract…)
Topic Distribution
Topics
Roles
Related Entities
Activity Timeline
October 2025
Authorizes a ~$3.3M increase to the construction services contract with Ragle, Inc. for additional work on the Cadiz Street and Riverfront Boulevard Bridge Improvements, raising the total contract to $26,016,940.77.
Authorize an increase in the construction services contract with Ragle, Inc. for additional work associated with the Cadiz Street and Riverfront Boulevard Bridge Improvements - Not to exceed $3,298,22
Briefing on authorizing a contract increase of approximately $3.3 million with Ragle, Inc. for additional work on the Cadiz Street and Riverfront Boulevard Bridge Improvements project, raising the total contract to $26,016,940.77, funded across three capital funds.
Dallas Water Utilities: Authorize an increase in the construction services contract with Ragle, Inc. for additional work associated with the Cadiz Street and Riverfront Boulevard Bridge Improvements -