April 2025
Consent Agenda
Authorizes Supplemental Agreement No. 1 increasing the professional services contract with Pacheco Koch for additional engineering services for the Cedar Creek Bridge replacement at Moore Street and erosion control easement surveys at Holliday Road and West Kiest Boulevard, raising the contract by $454,105 to a new total of $675,684.
…ns, specifications and contract documents, and construction observation for the Cedar Creek Bridge replacement at Moore Street and to prepare additional survey documents for erosion control easements at Hol…