February 2026

Consent Agenda

Authorizes a $1,421,849.94 increase in the construction services contract with BAR Constructors Inc. for additional pipeline bypass, clarifier rehabilitation, odor control repairs, and junction box/manhole installation at the Central Wastewater Treatment Plant.

…junction box and manholes to connect two existing pipelines associated with the Central Wastewater Treatment Plant Headworks and Primary Clarifiers Improvement Project - Not to exceed $1,421,849.94, from $50,432,956.25 to $51,854,806.19 - Financin…