Central Wastewater Treatment Plant Headworks and Primary Clarifiers Improvement Project
project
1 mention across 1 event
1 eventLast active Tracked since $1.4M city spending
Topic Distribution
Topics
consent agenda (1)
passed (1)
financial (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
February 2026
Consent Agenda
Authorizes an increase in a construction services contract with BAR Constructors Inc. for additional work at the Central Wastewater Treatment Plant, including bypass line installation, clarifier pipeline rehabilitation, odor control repairs, and junction box installation, increasing the contract by up to $1,421,849.94.
…junction box and manholes to connect two existing pipelines associated with the Central Wastewater Treatment Plant Headworks and Primary Clarifiers Improvement Project - Not to exceed $1,421,849.94, from $50,432,956.25 to $51,854,806.19 - Financin…
$1.4M