Dallas Floodway Charlie 2 Pump Station
Key facts
- Latest action
· City Council
Result: Approved · Amount: $761K
- Money
$761K in total financial activity across agenda items that mention this project.
Largest single item: $761K on (Authorizes a contract with Oncor Electric Delivery Company to extend standard and non-standard electrical delivery system facilities to serve the Dallas Floodway Charlie 2 Pump Station, funded by…)
Topics
Roles
Activity Timeline
February 2026
Authorizes a contract with Oncor Electric Delivery Company to extend standard and non-standard electrical delivery system facilities to serve the Dallas Floodway Charlie 2 Pump Station, funded by the Storm Drainage Management Capital Construction Fund.
…andard delivery system facilities (split-bus, two-way feed scheme) to serve the Dallas Floodway Charlie 2 Pump Station - Not to exceed $761,007.81 - Financing: Storm Drainage Management Capital Cons…