Mill Creek / Peaks Branch / State Thomas Drainage Relief Tunnel
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
View network map
Loading network map…
Activity Timeline
September 2026
Authorizes Supplemental Agreement No. 3 to the professional services contract with Black & Veatch Corporation for additional engineering and construction management services for the Mill Creek / Peaks Branch / State-Thomas Drainage Relief Tunnel Project, increasing the contract by up to $5,555,000 from $32,301,000 to $37,856,000. Financing is from the Flood Protection and Storm Drainage Facilities Fund.
Authorize Supplemental Agreement No. 3 to the professional services contract with Black & Veatch Corporation to provide additional engineering and construction management services required for the Mil
January 2026
A briefing on the construction progress of the Mill Creek/Peaks Branch/State Thomas Drainage Relief Tunnel, presented by the Director of Dallas Water Utilities.
Mill Creek / Peaks Branch / State Thomas Drainage Relief Tunnel Construction Update [Sarah Standifer, Director, Dallas Water Utilities]