Taxiway Charlie (Taxiway C) Phase 2 Reconstruction Project
Also known as: Taxiway C Phase 2 Reconstruction, Taxiway C Phase 2
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
Location
View network map
Loading network map…
Activity Timeline
June 2025
Authorizes acceptance of a $6,000,000 FAA Airport Improvement Program grant under the Bipartisan Infrastructure Law for the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field, including establishment of appropriations and execution of the grant agreement.
…ance Listing No. 20.106) in the amount of $6,000,000.00 for the construction of Taxiway Charlie (Taxiway C) Phase 2 Reconstruction Project where the performance period shall be for four years from the date of acceptanc…
May 2025
Authorization for a construction services contract with Flatiron Dragados Constructors, Inc. (lowest of three bidders) for the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field, not to exceed $20,536,102.86, funded through three aviation funds.
Authorize (1) a construction services contract for the demolition, removal, reconstruction, realignment, and rehabilitation of Taxiway Charlie, and for connection taxiways services for the Taxiway Cha
Authorization of a $20.5 million construction services contract with Flatiron Dragados Constructors for the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field, with associated appropriations across aviation grant, construction, and passenger facility charge funds.
Department of Aviation: Authorize (1) a construction services contract for the demolition, removal, reconstruction, realignment, and rehabilitation of Taxiway Charlie, and for connection taxiways serv
April 2025
Authorizes acceptance of a $10 million FAA Airport Improvement Program grant under the Bipartisan Infrastructure Law for the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field, with a four-year performance period and corresponding appropriations.
…nce Listing No. 20.106) in the amount of $10,000,000.00 for the construction of Taxiway Charlie Phase 2 Reconstruction Project where the performance period shall be fo…