Trinity Strand Trail Phase II
project
1 mention across 1 event
1 eventLast active Tracked since $155K city spending
Topic Distribution
Topics
parks (1)
contract (1)
transportation (1)
Roles
mentioned (1)
Related Entities
View network map
Loading network map…
Activity Timeline
February 2025
Consent Agenda
Decrease in the construction services contract with RoeschCo Construction LLC for Trinity Strand Trail Phase II (Inwood Road DART Station to Turtle Creek Boulevard) by $155,400 due to scope changes including deletion of traffic signal foundations, addition of pole protection pads, removal of cable railings, and replacement of ADA-compliant ramp materials.
Authorize a decrease in the construction services contract with RoeschCo Construction LLC for the construction of the Trinity Strand Trail Phase II, from Inwood Road DART Station to Turtle Creek Boule
$155K