ORDINANCES (CATEGORY) – NUMBERS 7 Through 48
Ordinance appropriating additional funds from the Water & Sewer System Consolidated Construction Fund and approving a First Amendment to the engineering services contract with Ardurra Group, Inc. for CRMP CIP Package 4, including the Eddington Lift Station replacement, force main, storage tank and Wet Weather Facility lift station.
ORDINANCE appropriating $9,031,494.00 out of Water & Sewer System Consolidated Construction Fund, as additional appropriation; approving and authorizing First Amendment to Professional Engineering Ser
$9.0M