Advanced Metering Infrastructure System
project
1 mention across 1 event
1 eventLast active Tracked since $5.5M city spending
Topic Distribution
Topics
utilities (1)
contract (1)
budget (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
October 2026
ORDINANCES (CATEGORY) – NUMBERS 10 Through 43
Appropriates an additional $5,500,000 from the Water & Sewer System Consolidated Construction Fund to the contract with Sensus USA, Inc. for installing the Advanced Metering Infrastructure System, amending Ordinance 2020-0992 and setting a new maximum contract amount.
ORDINANCE appropriating $5,500,000.00 out of Water & Sewer System Consolidated Construction Fund as an additional appropriation to contract between the City of Houston and SENSUS USA, INC for Installa
$5.5M