Chocolate Bayou Wastewater Treatment Plant Improvements
project
1 mention across 1 event
1 eventLast active Tracked since $167K city spending
Topic Distribution
Topics
utilities (1)
contract (1)
budget (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
October 2026
ORDINANCES (CATEGORY) – NUMBERS 10 Through 43
Appropriates $167,091.75 from the Water & Sewer System Consolidated Construction Fund and approves a First Amendment to the Trilogy Engineering Services, LLC professional engineering contract for Chocolate Bayou Wastewater Treatment Plant Improvements, including CIP cost recovery.
ORDINANCE appropriating $167,091.75 out of Water & Sewer System Consolidated Construction Fund, as additional appropriation; approving and authorizing First Amendment to Professional Engineering Servi
$167K