FY2025 Street & Drainage (SDR) Work Order Contract #4 (Rider)
Key facts
- Latest action
· City Council
Result: ORDINANCE 2026-0012 ADOPTED; all voting aye, nays none · Amount: $5.8M
- Money
$5.8M in total financial activity across agenda items that mention this project.
Largest single item: $5.8M on (Appropriates funding and awards Grava, LLC a work order contract for FY2025 street and drainage work, including related CIP cost recovery, contingency, and testing services.)
Topic Distribution
Topics
Roles
Related Entities
Activity Timeline
January 2026
Appropriates funding and awards Grava, LLC a work order contract for FY2025 street and drainage work, including related CIP cost recovery, contingency, and testing services.
ORDINANCE appropriating $5,750,000.00 out of Dedicated Drainage and Street Renewal Capital Fund - Drainage Charge; awarding contract to GRAVA, LLC for FY2025 Street & Drainage (SDR) Work Order Contrac