April 2026

ACCEPT WORK (CATEGORY) – NUMBERS 1 Through 4

Accept completed work and authorize any final contract payment for rehabilitating the John F. Kennedy Lift Station and abandoning and diverting flow from John F. Kennedy No. 2 Lift Station.

RECOMMENDATION from Director Houston Public Works that Houston City Council accept the work and authorize final payment, if any, of the contract with SERVOX, LLC for Rehabilitation of John F. Kennedy