Keegans Bayou Wastewater Treatment Plant Expansion
project
1 mention across 1 event
1 eventLast active Tracked since $195K city spending
Topic Distribution
Topics
utilities (1)
contract (1)
budget (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
September 2026
ORDINANCES (CATEGORY) – NUMBERS 11 Through 28
Appropriates $194,673 from the Water & Sewer System Consolidated Construction Fund and approves a first amendment to the MBROH Engineering contract for professional engineering services for the Keegans Bayou Wastewater Treatment Plant Expansion.
ORDINANCE appropriating $194,673.00 out of Water & Sewer System Consolidated Construction Fund, as additional appropriation; approving and authorizing First Amendment to contract with MBROH ENGINEERIN
$195K