Municue

Keegans Bayou Wastewater Treatment Plant Expansion

project
1 mention across 1 event
1 eventLast active Tracked since $195K city spending

Topic Distribution

Topics

utilities (1)
contract (1)
budget (1)

Roles

mentioned (1)

Activity Timeline

September 2026

ORDINANCES (CATEGORY) – NUMBERS 11 Through 28

Appropriates $194,673 from the Water & Sewer System Consolidated Construction Fund and approves a first amendment to the MBROH Engineering contract for professional engineering services for the Keegans Bayou Wastewater Treatment Plant Expansion.

ORDINANCE appropriating $194,673.00 out of Water & Sewer System Consolidated Construction Fund, as additional appropriation; approving and authorizing First Amendment to contract with MBROH ENGINEERIN

$195K