Nottingham Park and Community Center
Key facts
- Latest action
· City Council
Result: ORDINANCE 2026-0153 ADOPTED · Amount: $12.2M
- Money
$12.2M in total financial activity across agenda items that mention this project.
Largest single item: $12.2M on (Appropriates funds and authorizes a construction manager at risk contract to build the new Nottingham Park and Community Center, including construction, inspection, testing, civic art, and…)
Topic Distribution
Topics
Roles
Related Entities
Activity Timeline
February 2026
Appropriates funds and authorizes a construction manager at risk contract to build the new Nottingham Park and Community Center, including construction, inspection, testing, civic art, and contingency costs.
ORDINANCE appropriating $12,197,977.00 out of Parks Consolidated Construction Fund; approving and authorizing contract with TIMES CONSTRUCTION, INC to provide Construction Manager At Risk Services for