October 2026

Resolution

Authorizes a three-year natural gas supply agreement with Kinder Morgan Tejas Pipeline LLC for the city's gas distribution system, delivery November 1, 2026 through November 1, 2029, at an estimated cost of $75 million.

…as Pipeline LLC, Houston, Texas, at an estimated cost of $75,000,000.00 for the Corpus Christi gas distribution system for the delivery period beginning November 1, 2026, and ending November 1, 2029…

$75.0M