Discussion Regarding Holly Train Trestle to Tourism Trail

inactive
site_specificSignificantParks and Recreation Advisory Committee
The Parks and Recreation Advisory Committee is discussing a proposal to develop the Holly Train Trestle into a public tourism trail. This project would enhance recreational access and leverage a historic structure for community benefit and visitor engagement.
3 eventsFirst seen Jan 14, 2026Last activity Apr 8, 2026File #: 25-1898
Topics
transportation
parks
development

Get notified on new hearings, votes, or status changes for this matter.

Actions

Showing all 4 actions. Filter by: , , , .

Attorney
As of Apr 2026

Verify Flour Bluff trail grant deadline risk

Context: Assistant Director Sergio Gonzalez told the committee on January 14, 2026 that grant requirements mandate construction be initiated by August of this year.

Recommended: Pull the underlying grant agreement to find the forfeiture or extension clause — as of the April 8, 2026 meeting the design was still only 90% complete with lighting maintenance and bollard placement unresolved, leaving little room before the stated construction-start deadline.

Source: Parks and Recreation Advisory Committee — Apr 08, 2026 →
Journalist
As of Apr 2026

Ask if Flour Bluff trail will meet grant deadline

Context: The committee discussed this at the January 14, March 11, and April 8, 2026 meetings, recording 'no action was taken' each time it was noted, while the grant's construction-start deadline is August of this year.

Recommended: Contact PARD directly for the current construction timeline — this item has now gone before the advisory committee three times without a single vote, and the last public update left lighting maintenance ownership and bollard placement undecided just months before the funding deadline.

Source: Parks and Recreation Advisory Committee — Apr 08, 2026 →
Lobbyist
As of Apr 2026

Push for design changes before Flour Bluff trail locks in

Context: Jay Gardner reported April 8, 2026 that design plans were 90% complete and pointed to the upcoming Flour Bluff Citizens Council meeting as a venue for input, while Sergio Gonzalez set the August construction-start deadline on January 14, 2026.

Recommended: Raise any desired changes to lighting, bollard placement, or the parking lot layout with Assistant Director Sergio Gonzalez or through the Flour Bluff Citizens Council immediately — design was already 90% complete on April 8 and the grant's August construction deadline will force final sign-off within weeks.

Source: Parks and Recreation Advisory Committee — Apr 08, 2026 →
Resident
As of Apr 2026

Weigh in on Flour Bluff trail lighting and bollards

Context: At the April 8, 2026 meeting, committee members discussed trail lighting placement, who will maintain it (possibly AEP), bollard concerns, and changes to the existing parking lot, with Jay Gardner noting the design was 90% complete.

Recommended: Contact PARD now about where trail lighting and bollards will be placed near your property, and how the existing parking lot will change — these were still open questions as of April 8 and the design is nearly finalized.

Source: Parks and Recreation Advisory Committee — Apr 08, 2026 →

Timeline

Hearing
No action was taken on this item.

Discussion Regarding Holly Train Trestle to Tourism Trail

Vote: 0 for, 0 against

discussion only; no action was taken

Hearing
To Be Introduced

Discussion Regarding Holly Train Trestle to Tourism Trail

Hearing
No action was taken on this item

Discussion Regarding Holly Train Trestle to Tourism Trail

Vote: 0 for, 0 against

discussion only; no action taken