Alta Mesa Pump Station

location
1 mention across 1 event
1 eventLast active Tracked since $64.8M city spending

Topic Distribution

Topics

utilities (1)
budget (1)
contract (1)

Roles

mentioned (1)
View network map

Loading network map…

Activity Timeline

October 2026

General - Consent Items

Authorizes Change Order No. 7 ($114,135) and 17 additional calendar days to the ACME Electric contract for the Westside Water Treatment Plant generators and emergency preparation project Part 2, raising the contract to $23,875,427.38, with a related appropriation ordinance.

…atment Plant Generators and Emergency Preparation Plan Project: Part 2, for the Alta Mesa Pump Station for a revised contract amount of $23,875,427.38; and Adopt the attached appropr…

$64.8M