Westside Water Treatment Plant Generators and Emergency Preparation Plan Project: Part 2
project
1 mention across 1 event
1 eventLast active Tracked since $199K city spending
Topic Distribution
Topics
utilities (1)
contract (1)
budget (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
May 2026
Award Of Contract Consent
The city authorizes Change Order No. 5 with Winston Electric, Inc. (dba ACME Electric Company) increasing the Westside Water Treatment Plant Generators and Emergency Preparation Plan Project Part 2 contract by $198,741.76 to a revised total of $23,676,787.33 and extending the schedule by 55 calendar days.
(CD 9) Authorize Execution of Change Order No. 5 in the Amount of $198,741.76 to a Contract with Winston Electric, Inc. dba ACME Electric Company, for the Westside Water Treatment Plant Generators and