Award Of Contract Consent
Authorizes a $2,387,411.79 change order and 113 additional calendar days under the construction manager at risk agreement with Sundt Construction for the Cromwell Marine Creek Road project, along with a corresponding appropriation ordinance and Capital Improvement Program amendment.
…with Sundt Construction, Inc., for the Cromwell Marine Creek Road Project, from Boat Club Road (Farm to Market Road 1220) to Marine Creek Parkway, Adopt Appropriation Ordinance, and Amend the Fiscal Ye…