Municue

Sundt Construction, Inc.

organization
2 mentions across 2 events
2 eventsLast active Tracked since $22.0M city spending

Mention Frequency

Topic Distribution

Topics

contract (2)
budget (2)
utilities (1)
transportation (1)
bond (1)

Roles

vendor (2)
View network map

Loading network map…

Activity Timeline

May 2026

Award Of Contract Consent
vendor

Authorizes a $19,608,045.85 contract with S.Y.B. Construction Co., Inc. for cast iron water main replacement near the Holly-North Side Pump Station, an amendment to Freese and Nichols' engineering agreement, a reimbursement resolution for future debt, and an appropriation ordinance for the Water Capital Improvement Program.

(CD 2) Authorize Execution of a Contract with S.Y.B. Construction Co., Inc. in the Amount of $19,608,045.85 for 16-36 Inch Cast Iron Water Main Replacement in Holly-North Side Pump Station, Part 1, Au

$19.6M

March 2026

Award Of Contract Consent
vendor

Authorizes a $2,387,411.79 change order and 113-day extension under the Construction Manager at Risk agreement with Sundt Construction for the Cromwell Marine Creek Road Project, along with an appropriation ordinance and Capital Improvement Program amendment.

(CD 2 and CD 7) Authorize Execution of a Change Order for Extra Work in the Amount of $2,387,411.79 and the Addition of 113 Calendar Days Under the Construction Manager at Risk Agreement with Sundt Co

$2.4M