March 2026

Award Of Contract Consent
vendor

Authorizes a $2,387,411.79 change order and 113 additional calendar days to the Construction Manager at Risk Agreement with Sundt Construction, Inc. for the Cromwell Marine Creek Road Project, while also adopting an appropriation ordinance and amending the FY 2026-2030 Capital Improvement Program.

(CD 2 and CD 7) Authorize Execution of a Change Order for Extra Work in the Amount of $2,387,411.79 and the Addition of 113 Calendar Days Under the Construction Manager at Risk Agreement with Sundt Co