May 2026

Award Of Contract Consent

The city seeks to authorize a $19.6M construction contract with S.Y.B. Construction Co., Inc. and a $320K engineering amendment with Freese and Nichols, Inc. for cast iron water main replacement at Holly-North Side Pump Station Part 1, while also adopting a future debt reimbursement resolution and a capital improvement appropriation ordinance.

(CD 2) Authorize Execution of a Contract with S.Y.B. Construction Co., Inc. in the Amount of $19,608,045.85 for 16-36 Inch Cast Iron Water Main Replacement in Holly-North Side Pump Station, Part 1, Au

$19.6M