May 2026
Ratifies a First Amendment to the Biogas Purchase and Sale Agreement with Kinder Morgan Arlington RNG LLC (formerly Renovar Arlington, LTD), extending the term five additional years for biogas supply from the Village Creek Water Reclamation Facility.
…, to Extend Term for an Additional Five Years for the Supply of Biogas from the Village Creek Water Reclamation Facility
April 2026
Authorizes Change Order No. 1 adding $627,010 to Solid Bridge Construction's contract for the 3rd Main to West Fork Trunk Mains project, bringing the total to $10,123,788, and adopts a resolution expressing intent to reimburse expenditures with future debt proceeds along with an appropriation ordinance for the Water CIP.
…ed Contract Amount of $10,123,788.00 for the 3rd Main to West Fork Trunk Mains (Village Creek Water Reclamation Facility Biosolids Facility Bank Stabilization) Project…
March 2026
Authorizes a vendor service agreement with Automation Nation, Inc. for up to $485,045.00 annually for software licensing, maintenance, technical support, and professional services to manage sludge treatment in the biosolids operation at the Village Creek Reclamation Facility.
…reatment Process of Sludge in the Biosolids Operation at the Water Department’s Village Creek Reclamation Facility
Authorizes Amendment No. 1 totaling $503,696 to an engineering agreement with Freese and Nichols, Inc. for improvements to digesters at the Village Creek Water Reclamation Facility.
(CD 5) Authorize Execution of Amendment No. 1 in the Amount of $503,696.00 to an Engineering Agreement with Freese and Nichols, Inc. for the Village Creek Water Reclamation Facility Digester Improveme
January 2026
Authorizes Amendment No. 7 adding $357,780 to an engineering agreement with Freese and Nichols, Inc. for the Village Creek Water Reclamation Facility Biosolids Facility Bank Stabilization project, accompanied by an appropriation ordinance funding Water's portion of the FY2026–2030 Capital Improvement Program.
(CD 5) Authorize Execution of Amendment No. 7 in the Amount of $357,780.00 to an Engineering Agreement with Freese and Nichols, Inc. for the 3rd Main to West Fork Trunk Mains (Village Creek Water Recl