Activity Timeline

April 2026

Award Of Contract Consent
vendor

Authorizes Change Order No. 1 adding $627,010 to Solid Bridge Construction's contract for the 3rd Main to West Fork Trunk Mains project, bringing the total to $10,123,788, and adopts a resolution expressing intent to reimburse expenditures with future debt proceeds along with an appropriation ordinance for the Water CIP.

(CD 5) Authorize Execution of Change Order No. 1, in the Amount of $627,010.00, to a Contract with Solid Bridge Construction, LLC for a Revised Contract Amount of $10,123,788.00 for the 3rd Main to We

$627K