Activity Timeline
April 2026
Authorizes Change Order No. 2 with Woody Contractors, Inc. increasing the construction contract by $571,464.40 and adding 80 calendar days for the 2022 Bond Year 2 - Contract 12 Project, bringing the revised total to $9,699,312.15, with accompanying appropriation ordinances and Capital Improvement Program amendment.
(CD 9) Authorize Execution of Change Order No. 2 in the Amount of $571,464.40, and the Addition of 80 Calendar Days to the Construction Contract with Woody Contractors, Inc. for the 2022 Bond Year 2 -
March 2026
Authorizes a $15,683,491.90 contract with Stabile & Winn, Inc. for combined street paving improvements and water/sanitary sewer main replacements under the 2022 Bond Program Year 2, Contract 7, along with appropriation ordinances and Capital Improvement Program amendments.
…reet Paving Improvements and Water and Sanitary Sewer Main Replacements for the 2022 Bond Year 2 – Contract 7 Project; Adopt Appropriation Ordinances to Effect a Portion of Water Department…
Correction to a prior council communication (26-0071) awarding combined street paving, stormwater, and water/sanitary sewer main replacement work for the 2022 Bond Year 3 – Contract 13 Project to 2R Construction Services, LLC.
(CD 5 and CD 11) Correct Mayor & Council Communication 26-0071 to Award Combined Street Paving Improvements, Stormwater Improvements, and Water and Sanitary Sewer Main Replacements for the 2022 Bond Y