March 2026
Authorizes a $15,683,491.90 construction contract with Stabile & Winn, Inc. for combined street paving improvements and water/sanitary sewer main replacements in Council District 9 under the 2022 Bond Program, along with appropriation ordinances for Water Department and street repair funding.
(CD 9) Authorize Execution of a Contract with Stabile & Winn, Inc., in the Amount of $15,683,491.90, for Combined Street Paving Improvements and Water and Sanitary Sewer Main Replacements for the 2022
February 2026
Authorizes a $2,026,734.45 contract with Stabile & Winn, Inc. for street paving improvements and water/sewer main replacements in Council District 9, accepts $2,000,000 from the Southside TIF to support the street repair program bringing the revised total program amount to $18,000,000, and adopts related appropriation ordinances.
(CD 9) Authorize Execution of a Contract with Stabile & Winn, Inc., in the Amount of $2,026,734.45, for Combined Street Paving Improvements and Water and Sanitary Sewer Main Replacements for Round Six