Award Of Contract - Consent Items
Authorizes Change Order No. 3 and 75 additional calendar days for Stabile & Winn's 2022 Bond Year 3 Contract 14 construction project. The item increases the contract amount, transfers stormwater capital funding, and amends the capital improvement program.
…75 Calendar Days to the Construction Contract with Stabile & Winn, Inc. for the 2022 Bond Year 3 – Contract 14 Project for a Revised Contract Amount of $10,193,602.75, Adopt Appropriation Or…
$12.5M