February 2026
Award Of Contract Consent
Authorizes a $2,026,734.45 contract with Stabile & Winn, Inc. for street paving improvements and water/sewer main replacements in Council District 9, accepts $2,000,000 from the Southside TIF to support the street repair program bringing the revised total program amount to $18,000,000, and adopts related appropriation ordinances.
…mprovements and Water and Sanitary Sewer Main Replacements for Round Six of the Council District 9 Street Repair and Reconstruction Program and Near Southside Medical District Water and Sanitary Sewer Main Improvements…
$2.0M