36-Inch Eastside II Prestressed Concrete Cylinder Pipe Water Main & Critical Replacement Project
project
1 mention across 1 event
1 eventLast active Tracked since $210K city spending
Topic Distribution
Topics
utilities (1)
contract (1)
development (1)
Roles
mentioned (1)
Related Entities
Activity Timeline
June 2026
Award Of Contract Consent
Authorizes Change Order No. 2 adding $210,248.50 to the contract with Circle C Construction Company for the 36-Inch Eastside II water main replacement project, along with a capital improvement appropriation ordinance.
(CD 5) Authorize Execution of Change Order No. 2 with William J. Schultz, Inc. dba Circle C Construction Company in the Amount of $210,248.50 for the 36-Inch Eastside II Prestressed Concrete Cylinder
$210K