June 2026
Authorizes a reimbursement agreement with Atmos Energy Corporation for up to $1,022,486.25 to relocate a gas pipeline to accommodate the WJ Boaz Road Widening Improvements Project, funded through the 2022 Bond Program.
…an Amount Up to $1,022,486.25 for a Gas Pipeline Relocation to Accommodate the WJ Boaz Road Widening Improvements Project (2022 Bond Program)
Authorizes a $22,288,804.77 construction contract with McCarthy Building Companies for widening Bonds Ranch Road from Wagley Robertson Road to Hawks Landing Road, funded through the 2022 Bond Program.
(CD 10) Authorize Execution of a Contract with McCarthy Building Companies, Inc. in the Amount of $22,288,804.77 for the Bonds Ranch Road Widening Improvements Project from Wagley Robertson Road to Ha