2 mentions across 2 events
2 eventsLast active Tracked since $5.1M city spending

Mention Frequency

Topic Distribution

Topics

utilities (2)
contract (2)
transportation (1)
budget (1)
bond (1)

Roles

mentioned (2)
View network map

Loading network map…

Activity Timeline

May 2026

Award Of Contract Consent

Authorizes a $5,125,395.00 contract with R & D Burns Brothers, Inc. for the Water and Sanitary Sewer Replacements Contract 2023, WSM-A Project, and adopts an appropriation ordinance for the Water Department's contribution to the FY2026-2030 Capital Improvement Program.

(CD 9) Authorize Execution of a Contract with R & D Burns Brothers, Inc., in the Amount of $5,125,395.00, for Water and Sanitary Sewer Replacements Contract 2023, WSM-A Project, and Adopt Appropriatio

$5.1M

April 2026

Award Of Contract Consent

Authorizes a $7,012,695.20 construction contract with Venus Construction Company for water and sanitary sewer replacement (WSM-I Project), adopts appropriation ordinances for the Water Department's capital improvement contribution, and amends the Transportation and Public Works CIP under the 2022 Bond Program.

(CD 11) Authorize Execution of a Contract with Venus Construction Company, in the Amount of $7,012,695.20, for Water and Sanitary Sewer Replacement Contract 2019, WSM-I Project, Adopt Resolution Expre