Activity Timeline
September 2026
Authorizes Change Order No. 4 in the amount of $297,494.95 and 180 additional days to a contract with Venus Construction Company, Inc. for the Water and Sanitary Sewer Replacement Contract 2020, WSM-M project, raising the contract to $10,400,495.70, and adopts an appropriation ordinance funding the change from Water and Sewer PayGo funds.
Venus Construction Company, Inc. Water and Sewer Contract Change Order 4
April 2026
Authorizes a $7,012,695.20 construction contract with Venus Construction Company for water and sanitary sewer replacement (WSM-I Project), adopts appropriation ordinances for the Water Department's capital improvement contribution, and amends the Transportation and Public Works CIP under the 2022 Bond Program.
(CD 11) Authorize Execution of a Contract with Venus Construction Company, in the Amount of $7,012,695.20, for Water and Sanitary Sewer Replacement Contract 2019, WSM-I Project, Adopt Resolution Expre